Refuse Disposal Permit
New - Refuse Disposal Permit - Municipal Landfill
Expected Fee
$0
Estimated Processing Time
36 Months
-
Submit a complete application form
-
Submit a hydrogeological assessment of the site
-
Submit a conceptual facility plan
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed landfill
-
Submit one year of ground water data
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Renew - Refuse Disposal Permit - Municipal Landfill
Expected Fee
$0
Estimated Processing Time
36 Months
-
Submit a complete application form
-
Submit a hydrogeological assessment of the site
-
Submit a conceptual facility plan
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed landfill
-
Submit one year of ground water data
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Modification - Refuse Disposal Permit - Municipal Landfill
Expected Fee
$0
Estimated Processing Time
36 Months
-
Submit a complete application form
-
Submit a hydrogeological assessment of the site
-
Submit a conceptual facility plan
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed landfill
-
Submit one year of ground water data
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
New - Refuse Disposal Permit - Rubble Landfill
Expected Fee
$0
Estimated Processing Time
36 Months
-
Submit a complete application form
-
Submit a hydrogeological assessment of the site
-
Submit a conceptual facility plan
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed landfill
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Renew - Refuse Disposal Permit - Rubble Landfill
Expected Fee
$0
Estimated Processing Time
36 Months
-
Submit a complete application form
-
Submit a hydrogeological assessment of the site
-
Submit a conceptual facility plan
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed landfill
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Modification - Refuse Disposal Permit - Rubble Landfill
Expected Fee
$0
Estimated Processing Time
36 Months
-
Submit a complete application form
-
Submit a hydrogeological assessment of the site
-
Submit a conceptual facility plan
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed landfill
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
New - Refuse Disposal Permit - Industrial Landfill
Expected Fee
$0
Estimated Processing Time
24 Months
-
Submit a complete application form
-
Submit a hydrogeological assessment of the site
-
Submit a conceptual facility plan
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed landfill
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Renew - Refuse Disposal Permit - Industrial Landfill
Expected Fee
$0
Estimated Processing Time
24 Months
-
Submit a complete application form
-
Submit a hydrogeological assessment of the site
-
Submit a conceptual facility plan
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed landfill
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Modification - Refuse Disposal Permit - Industrial Landfill
Expected Fee
$0
Estimated Processing Time
24 Months
-
Submit a complete application form
-
Submit a hydrogeological assessment of the site
-
Submit a conceptual facility plan
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed landfill
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
New - Refuse Disposal Permit - Land Clearing Debris Landfill
Expected Fee
$0
Estimated Processing Time
12 Months
-
Submit a complete application form
-
Submit a hydrogeological assessment of the site
-
Submit a conceptual facility plan
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed landfill
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Renew - Refuse Disposal Permit - Land Clearing Debris Landfill
Expected Fee
$0
Estimated Processing Time
12 Months
-
Submit a complete application form
-
Submit a hydrogeological assessment of the site
-
Submit a conceptual facility plan
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed landfill
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Modification - Refuse Disposal Permit - Land Clearing Debris Landfill
Expected Fee
$0
Estimated Processing Time
12 Months
-
Submit a complete application form
-
Submit a hydrogeological assessment of the site
-
Submit a conceptual facility plan
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed landfill
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
New - Refuse Disposal Permit - Incinerator
Expected Fee
$0
Estimated Processing Time
12 Months
-
Submit a complete application form
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed facility
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Renew - Refuse Disposal Permit - Incinerator
Expected Fee
$0
Estimated Processing Time
12 Months
-
Submit a complete application form
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed facility
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Modification - Refuse Disposal Permit - Incinerator
Expected Fee
$0
Estimated Processing Time
12 Months
-
Submit a complete application form
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed facility
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
New - Refuse Disposal Permit - Transfer Station
Expected Fee
$0
Estimated Processing Time
7 Months
-
Submit a complete application form
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed facility
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Renew - Refuse Disposal Permit - Transfer Station
Expected Fee
$0
Estimated Processing Time
7 Months
-
Submit a complete application form
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed facility
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Modification - Refuse Disposal Permit - Transfer Station
Expected Fee
$0
Estimated Processing Time
7 Months
-
Submit a complete application form
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed facility
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
New - Refuse Disposal Permit - Processing Facility
Expected Fee
$0
Estimated Processing Time
9 Months
-
Submit a complete application form
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed facility
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Renew - Refuse Disposal Permit - Processing Facility
Expected Fee
$0
Estimated Processing Time
9 Months
-
Submit a complete application form
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed facility
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Modification - Refuse Disposal Permit - Processing Facility
Expected Fee
$0
Estimated Processing Time
9 Months
-
Submit a complete application form
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed facility
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
New - Refuse Disposal Permit - Processing & Transfer Facility
Expected Fee
$0
Estimated Processing Time
9 Months
-
Submit a complete application form
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed facility
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Renew - Refuse Disposal Permit - Processing & Transfer Facility
Expected Fee
$0
Estimated Processing Time
9 Months
-
Submit a complete application form
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed facility
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315
Modification - Refuse Disposal Permit - Processing & Transfer Facility
Expected Fee
$0
Estimated Processing Time
9 Months
-
Submit a complete application form
-
Submit detailed engineering plans and specifications
-
Submit an operating manual for the proposed facility
The Solid Waste Program Operations Division
Land and Materials Administration
[email protected]
(410) 537-3315